FERC Rejects PJM’s Plan to Curtail New Data Centers First

The Federal Energy Regulatory Commission on October 9, 2026 accepted two pieces of PJM’s large load filing, a 50 megawatt definition and a registry, and rejected the rest: the curtailment service, the requirement to bring new capacity and the exemption rules that went with it. The registry took effect October 12.

BY EDITED BY ZED TRUONG9 MIN READ
SHARE

Direct answer

Direct answer to FERC rejects PJM IRAS

New data centers in PJM will not be curtailed first under a federal tariff, at least not yet. FERC found the plan reached into state authority over retail service and had not been shown to be nondiscriminatory, and it invited a refiling. What survived is visibility: every site at 50 megawatts or more now goes into a PJM registry that records its ramp, backup generation and supply contracts.

A long, windowless pale grey data center building seen from across a four-lane road, behind a black steel picket fence and a row of shrubs and trees, some with red autumn leaves, with boxy mechanical units and railings along the roofline and a second building with rooftop units further left, under a pale sky streaked with thin cloud.
IMAGE: VAHURZPU / CC BY-SA 4.0Data center buildings in Ashburn, Virginia, in October 2020, which the photographer identifies as Amazon Web Services facilities. On October 9, 2026 FERC accepted PJM’s 50 megawatt Large Load definition and registry and rejected its plan to curtail new large loads first. The order names no specific facility. Image: Vahurzpu / CC BY-SA 4.0.

What the Commission accepted, what it rejected, and why

On October 9, 2026 the Federal Energy Regulatory Commission issued an order in Docket No. ER26-3515-000, reported at 197 FERC ¶ 61,019, on the large load package PJM Interconnection, L.L.C. filed on August 13. PJM had asked for six things: a definition of Large Load, a Large Load Registry, Interim Resource Adequacy Service, a requirement that load serving entities serving New Large Load designate new capacity at least equal to that load’s peak, rules for Bring Your Own New Capacity arrangements, and an exclusion of Eligible New Large Load from the capacity demand curve starting with the 2029/2030 Delivery Year. The Commission accepted the first two, effective October 12, 2026 as PJM requested, and directed a compliance filing within 30 days. It rejected the other four, and it also severed and rejected, without prejudice, PJM’s separate definition of New Large Load, the term that would have marked which loads could be curtailed. The accepted definition is the one this desk described on September 7: end-use customer load with a cumulative peak of 50 megawatts or more at a single electrical site, with all affiliated load facilities within a one-mile radius treated as one site. The Commission rejected protests that the threshold should be higher, limited to data centers, or should spare legacy facilities near new ones, and left the method for measuring the mile to PJM’s manuals.

The order gives three reasons for the rejection. First, jurisdiction. The Federal Power Act leaves retail sales to the states, and the Commission found that the proposed tariff language appeared to place obligations directly on Eligible New Large Loads, which it said are for the most part retail customers, appeared to dictate which retail customers would be curtailed, and appeared to set a retail rate through the compensation it directed to those customers. The Commission said PJM’s transmittal letter described a narrower design that might have been within its authority, but that the tariff text did not match it, and that PJM’s answer did not engage with the gap. Second, discrimination: PJM had not produced sufficiently detailed evidence for treating load serving entities differently based on the characteristics of their retail customers, when its capacity market has historically procured for all network load alike. Third, the exemption itself: the Commission found PJM had not justified locking in a Bring Your Own New Capacity resource’s capacity accreditation for the life of the arrangement, and said the lock-in could leave the region short if a resource’s real contribution fell. Because the remaining pieces were, in its words, inextricably linked, it rejected them as a package. Commissioner David Rosner concurred, writing that a refiled plan must justify curtailing this load on a mandatory basis ahead of customers who volunteered for demand response, and that “homes, hospitals, and schools should never be curtailed before data centers.”

Why the registry, not the rejection, is what changes for an owner this month

The rejection removes terms that were never in force. The registry is in force now. Under the accepted design, the load serving entity for each Large Load must submit or cause to be submitted the Eligible Customer, a description of the load, its location, the in-service date of each increment, any peak shaving adjustment, the delivery point, the peak load quantity and ramp schedule, telemetry specifications, backup generation including fuel type and permitting limitations, contracts or service agreements between the load and the load serving entity, and contacts at the transmission owner, the electric distributor and the load serving entity. The Commission expects PJM to drop items that belonged to the rejected package, such as the amount of new capacity a load brought. The information is shared with state commissions, transmission owners, electric distributors, load serving entities, the market monitor and the Commission under PJM’s existing confidentiality rules, and PJM will publish only aggregated data. State consumer advocates do not get access under those rules, and the Commission declined to widen it. Industrial customers stay in the registry, but the order says only for informational purposes, since the curtailment service they objected to is gone.

The practical point for a data center owner, a powered land seller or a manufacturer near the 50 megawatt line is that a third party is now describing the site to the grid operator, and the owner may not see what was filed. The registry is how PJM forecasts load and plans transmission, so a ramp schedule entered loosely becomes a planning input. Two facts from the same week show why the grid side matters to real estate. On September 29 the Commission accepted PJM’s companion Reliability Backstop Procurement in Docket ER26-3380-000 but suspended it for five months, to an effective date of February 28, 2027, subject to refund and a paper hearing, and PJM said the procurement would not open on September 30 as planned and that timing is to be determined. And on October 13 and 14, with about 61,000 megawatts of generation out for maintenance by PJM’s count, PJM issued a Maximum Generation Alert and Pre-Emergency Load Management Actions, and said a Department of Energy emergency order allows it to direct data centers and other Large Loads onto backup generation if necessary. PSV did not read that Department of Energy order and reports its scope only as PJM describes it.

The workflow PSV would run now that the order is out

The register this desk proposed on September 7, one row per site a firm owns or is chasing in PJM, needs a revision rather than a rebuild. Inputs are the October 9 order, PJM’s compliance filing when it arrives, the September 29 backstop order, PJM’s operations notices, and the firm’s own site list with measured and forecast peak load. Columns that tracked the rejected terms (the ten-year price-taker obligation, the transferability rule, the March 1, 2027 proof deadline) are marked rejected with the order citation, not deleted, because a refiling may bring some of them back. New columns follow the registry: whether the site is a Large Load under the accepted definition including affiliated facilities within a mile, who the load serving entity is, the owner’s own version of each registry field, the date the owner confirmed the utility’s submission matches it, and any capacity or supply contract signed with the old rules in mind. The output is a short list per site of registry fields that differ between the owner’s records and what the utility reports.

The reviewer is whoever owns the utility relationship for the site, with counsel on any contract that references the rejected service by name. The approval gate is that no load quantity or ramp schedule goes to a utility for registry purposes until a named person signs the row, because those are the numbers PJM will plan against. An assistant does the volume work well: extracting the order’s accepted and rejected items into cells, diffing PJM’s compliance filing against the order, watching the docket for a refiling or rehearing request, and flagging contracts that mention the rejected terms. It should not decide whether a contract’s conditions are triggered by a rejection, should not treat Commission guidance on a possible refiling as a rule, and should not estimate what a refiled plan will say. PSV ran no model on this order, tested no product, and promises no cost, schedule, reliability or approval outcome.

What stays with a person, and what the order leaves open

The operator read

Finish with the judgment call.

The reported facts are above. Enter your email for PSV's operator conclusion and a year of access to every newsroom brief.

THIS ARTICLEALL PSV BRIEFSNO CARD REQUIRED
Send the operator read

Free. No card. Privacy policy. Unsubscribe anytime.

Dispatch the read

Keep the operator view in your deal room.

CRE AI Instituteby PSVLive

Build the workflow behind this analysis. Train with the operators doing it.

Real deal files, live builds, and production-ready CRE AI workflows inside the CRE AI Institute.

Clear answers

Common questions about FERC rejects PJM IRAS

What did FERC decide on PJM’s large load plan?

In an order issued October 9, 2026 in Docket ER26-3515-000, FERC accepted PJM’s definition of Large Load and its Large Load Registry, effective October 12, 2026, and rejected Interim Resource Adequacy Service, the requirement to designate new capacity for New Large Load, the Bring Your Own New Capacity rules and the exclusion of that load from the capacity demand curve. It directed a compliance filing within 30 days and invited PJM to refile a modified plan.

Why did FERC reject PJM’s plan to curtail data centers first?

The order says the tariff language appeared to place obligations directly on new large loads, which are mostly retail customers, to dictate which retail customers would be curtailed, and to set a retail rate, all matters the Federal Power Act leaves to the states. It also found PJM had not shown the different treatment was not unduly discriminatory, and had not justified locking in the capacity accreditation of Bring Your Own New Capacity resources.

What does the PJM Large Load Registry collect about a data center?

The load serving entity reports the customer, a description and location of the load, in-service dates for each increment, peak load and ramp schedule, the delivery point, telemetry, backup generation including fuel type and permitting limits, contracts between the load and the load serving entity, and contacts. Access follows PJM’s existing confidentiality rules, and PJM publishes only aggregated data. The registry covers loads of 50 megawatts or more, counting affiliated facilities within one mile as one site.

Primary source record

These records support the reported facts in this brief. PSV’s CRE workflow interpretation and test plan are original analysis.

Topics

CRE POLICY NEWSFERC rejects PJM IRASFERC PJM large load order ER26-3515PJM Bring Your Own New Capacity rejectedPJM Large Load Registry data centerPJM data center curtailment FERC order October 2026

CRE POLICY NEWS

PJM’s Firm Power Exemption Is a 10 Year Commitment

PJM told this desk’s readers in July what its Board had directed. The filings themselves are now at the Federal Energy Regulatory Commission, in dockets ER26-3380-000 and ER26-3515-000, and the comment window closed on September 3. They contain terms the Board letter never stated, and the most consequential one is what a site has to promise to keep firm power.

Read PJM Bring Your Own New Capacity firm power

CRE POLICY NEWS

Maryland Puts Every 25 MW Data Center Through State Review

Governor Wes Moore signed Executive Order 01.01.2026.16 on September 23, putting any Maryland data center of 25 megawatts or more through one state review the moment it asks the state for a permit, incentive or letter of support. A new task force grades each project Aligned, Conditionally Aligned or Not Aligned on a public dashboard, and the governor will ask lawmakers to repeal the 2020 sales tax exemption.

Read Maryland data center executive order

CRE POLICY NEWS

Loudoun Leaves 15 Grandfathered Data Center Projects Alone

Loudoun County’s Board of Supervisors on October 6 took up a proposal to end early the 2025 rule that lets 15 pending data center site plans, 30 buildings and about 10.5 million square feet, proceed without a board vote. Staff warned of $45 million to $60 million in potential liability. The board changed nothing, and local outlets report it tabled a $200,000 audit of those projects 7-2.

Read Loudoun data center grandfathering

Cornerstone PSV guides on the workflows in this article.

Back to the CRE AI Newsroom