US data center moratorium tracker pauses, orders and large-load rules

Pacific Software Ventures' newsroom reads the orders, filings and dockets behind data center restrictions. This page collects them, with the trigger, the status and the primary source for each.

The short answer. This tracker lists 17 moratoriums and pauses, 13 of them passed or in effect, and New York's order is the first statewide freeze we reported. The most common state trigger is 25 MW, used by Massachusetts, Maryland and Pennsylvania.

Download the data as CSV. It is free to reuse with a link back. This is not a complete list of every local measure, and it is not legal advice.

17 records

Moratoriums and pauses on new data centers

A government has stopped, or is about to decide whether to stop, new applications or permits.

WhereWhat happenedTriggerUntilStatusDateSources
New York (statewide)Executive Order 62 pauses state environmental permits for new hyperscale data centers while the state writes a study and standards.50 MW or moreUp to one year from July 14, 2026In effectJuly 14, 2026Primary source
PSV story
Texas (statewide)The governor told the state environmental agency to pause all data center permits until ERCOT finishes its review, and said no other agency should move forward with approvals.All data center projectsNo end date. ERCOT's report is due December 10, 2026In effectSeptember 21, 2026Primary source
PSV story
Charlotte, North CarolinaCity Council extended its moratorium on new data center applications. Projects approved before June 8 and existing facilities are not covered.New applicationsOctober 18, 2027In effectOctober 26, 2026Primary source
PSV story
San Francisco, CaliforniaUrgency ordinance File No. 261021 bars any city approval for a data center, with exceptions for accessory computing and repair of existing sites.All new approvals45 days from about October 16, 2026. Check for an extensionIn effectOctober 16, 2026Primary source
PSV story
Anne Arundel County, MarylandBill 63-26 stops the county accepting new data center applications and repeals a 2022 tax break on data center equipment.New applicationsJanuary 31, 2028 at the latestPassedOctober 5, 2026Primary source
PSV story
Cheyenne and Arapaho Tribes, OklahomaCitizens voted on Resolution 100326ATC-004, a moratorium on new data centers on tribal land. News 9 reported it passed 261 to 83.All new data centers on tribal landThree years from October 3, 2026, or a later safeguarding resolutionPassedOctober 3, 2026Primary source
PSV story
Loudoun County, VirginiaThe board voted 7-1-1 to have staff draft a resolution pausing new legislative data center applications while it rewrites its zoning rules.

Update: The county deferred the resolution from its October 20 meeting to November 17. Loudoun County notice

New legislative applicationsUp to 12 months if adoptedPendingSeptember 15, 2026Primary source
PSV story
Seattle, WashingtonCity Council passed an emergency ordinance pausing new large data centers while the city studies their effects.Over 20 megavolt-amperes of power capacityOne year from June 2026. The council may extend it six monthsIn effectJune 9, 2026Seattle City Council
Denver, ColoradoCouncil Bill 26-0431 pauses applications for new primary-use data centers and expansions, while a working group drafts rules.New primary-use data centers and expansionsMay 21, 2027, unless rules arrive sooner or the council extends itIn effectMay 18, 2026Holland & Knight
Indianapolis (Marion County), IndianaThe Metropolitan Development Commission approved a moratorium on new data centers. The three projects already approved are unaffected.New data center approvalsAt least December 31, 2027In effectAugust 19, 2026WFYI
Cleveland, OhioCity Council extended its pause on new standalone data centers and expansions of existing ones, while the city writes rules.Standalone, principal-use data centersJanuary 29, 2027In effectOctober 19, 2026Government Technology
Minneapolis, MinnesotaCity Council paused new data centers across most of the city. Downtown projects of 350,000 square feet or less are exempt.New data centers outside the downtown exemptionReported to run until November 2026. Check for an extensionIn effectJune 25, 2026MPR News
Montgomery County, MarylandThe 11-member County Council voted unanimously for an 18-month moratorium on data center development.Data center development18 months from adoptionPassedJuly 28, 2026WTOP
Prince George's County, MarylandThe County Council barred its planning department from considering or approving data center applications.Data center applicationsUp to two years, or until the council passes rulesPassedJuly 7, 2026Inside Climate News
New York (legislature)The legislature passed S10642 and A11560, a one-year pause reaching smaller projects than the governor's order. Instead of acting on it, the governor issued Executive Order 62.20 MW or more of peak demandNot signed as of the source's July 23 updatePendingJune 4, 2026Davis Polk
Maine (statewide)The legislature passed LD 307, a statewide moratorium. The governor vetoed it, and the override failed on April 29. Her stated objection was the lack of an exemption for a project in Jay.Larger than 20 MWWould have run to November 2027VetoedApril 24, 2026Maine Morning Star
Georgia (statewide)Keisha Lance Bottoms, who campaigned on a statewide pause on new data center construction, won the governor's race. Democrats also won a 3 to 2 majority on the Public Service Commission.Not yet definedNo order issued as of this storyWatchNovember 3, 2026Primary source
PSV story

5 records

State orders and zoning that set conditions

Projects can still proceed, but only on new terms.

WhereWhat happenedTriggerUntilStatusDateSources
MassachusettsExecutive Order 658 bars state permits until a data center conforms with the governor's framework and files a reviewed community benefits agreement.Above 25 MW of peak demandSee the orderIn effectSeptember 8, 2026Primary source
PSV story
MarylandExecutive Order 01.01.2026.16 puts each project through one state review, graded on a public dashboard. The governor will ask lawmakers to repeal the 2020 sales tax exemption.25 MW or moreSee the orderIn effectSeptember 23, 2026Primary source
PSV story
PennsylvaniaExecutive Order 2026-05 removes data centers from the Permit Fast Track Program. The state will not issue a permit until local approvals are in hand.Over 25 MW of peak demandSee the orderIn effectAugust 18, 2026Primary source
PSV story
Prince William County, VirginiaZoning amendment DPA2026-00006 closes the data center overlay to expansion and routes new data centers outside it through a special use permit. The overlay shrinks by about 64 percent.New data centers outside the overlayZoning amendment, no end dateIn effectSeptember 22, 2026Primary source
PSV story
Prince William County, VirginiaThe Court of Appeals of Virginia held the three Digital Gateway rezoning ordinances void from the beginning, over a defective hearing notice. QTS later said it was terminating the project.One project, about 22 million square feetFinal: the county chose not to appealStruck downMarch 31, 2026Primary source
PSV story

7 records

Grid and federal rules on large loads

Who pays for power, and who gets it first.

WhereWhat happenedTriggerUntilStatusDateSources
Texas (ERCOT)A verification and audit of every data center in the interconnection process. The Public Utility Commission suspended the Batch Zero classification deadlines.Data centers in ERCOT's queueSee the orderIn effectAugust 20, 2026Primary source
PSV story
PJM region (FERC)FERC accepted a 50 MW large load definition and a registry, and rejected the curtailment service and the requirement to bring new capacity.50 MWRegistry took effect October 12, 2026Accepted in partOctober 9, 2026Primary source
PSV story
Tennessee Valley AuthorityThe board moved data centers onto their own rate. Officials described a roughly 10 percent increase and an upfront capacity charge. TVA's own release names none of those terms.New load above 5 MW, as describedOctober 1 start, as describedIn effectAugust 20, 2026Primary source
PSV story
WisconsinThe state commission approved a Very Large Customer tariff in docket 6630-TE-113 and made it mandatory.100 MW or more of annual demandSee the orderIn effectSeptember 4, 2026Primary source
PSV story
Arizona (APS)Microsoft told regulators that APS has been unable to commit to serve any new large load customer since January 1, 2024. APS's own brief describes a large queue of uncommitted customers.New large loadsRate case pendingWatchAugust 27, 2026Primary source
PSV story
United States (House)H.R. 9340, the Ratepayer Protection Act, would make campuses pay the full incremental cost of grid upgrades. The House passed it 417 to 3. A senator blocked fast passage the next day.100 MW or moreNot lawPendingSeptember 16, 2026Primary source
PSV story
United States (Senate)The Bipartisan American Affordability and Jobs Act would make large computing loads bear the full incremental cost of power and let states auction service.20 MW or moreIntroduced, not lawProposedSeptember 30, 2026Primary source
PSV story

12 campuses

Campuses where the record has a catch

Large projects from the same coverage, with the size and money as stated, and what the documents add.

CampusPartiesSizeMoneyWhat the record saysDateSources
HyperionRichland Parish, LouisianaMetaAbout 5 GW, 10 million square feetMore than $50 billionMeta's own stated figures.July 14, 2026Primary source
PSV story
PORTS Technology CampusPike County, OhioSB Energy, with an OpenAI affiliate as tenantAbout 4.25 GW of IT loadNVIDIA guaranties capped at $105 billion20-year lease, backed by NVIDIA residual value guaranties.August 17, 2026Primary source
PSV story
Project CamelliaEffingham County, GeorgiaOpenAI3.2 GW$20 billionThe county said five days later that no completed application had been submitted.July 22, 2026Primary source
PSV story
Project MatadorCarson County, TexasFermi, with TensorWave as first tenant222 MW first leaseAbout $6.5 billion of contracted revenueInitial 15-year term. A corrected release dropped a sentence about a guarantee.August 10, 2026Primary source
PSV story
Paducah SiteWestern KentuckyU.S. Department of Energy, Brookfield, NextEraUp to 1.8 GW of utility capacity, more than 1.2 GW of computeAbove $100 billion, as statedNo tenant named.July 29, 2026Primary source
PSV story
El Paso campusEl Paso, TexasMeta, BlackRock funds1 GWAbout $14 billionBlackRock funds own 80 percent. Meta's filing shows about $13 billion of residual value guarantees.July 28, 2026Primary source
PSV story
Beacon PointNueces County, TexasHut 81 GW campus$9.8 billion base-term value on the second leaseFully leased to one investment-grade tenant, per Hut 8.July 20, 2026Primary source
PSV story
Muskie Data CampusEastern KentuckyTeraWulf, Kentucky Power1 GW contracted, up from 500 MWSee the sourceSubject to state utility regulators.October 1, 2026Primary source
PSV story
Barber LakeColorado City, TexasCipher Digital, Fluidstack, an unnamed AI lab300 MWAbout $5.2 billion of added contracted revenueThe unnamed lab committed to years 11 to 20.September 25, 2026Primary source
PSV story
Project EagleGlendale, ArizonaCity of Glendale case ZON26-05About 160 acres, with eighteen natural gas turbinesSee the sourceNext to Luke Air Force Base. Turbines would power it until APS builds a substation, anticipated in 2030.

Update: The City Council approved the project at its October 27 meeting. KJZZ

September 24, 2026Primary source
PSV story
Project JupiterDoña Ana County, New MexicoStack Infrastructure, OracleSee the sourceSee the sourceOracle sent a force majeure notice that reportedly lets it defer some rent if power is late.September 26, 2026Primary source
PSV story

Method

How we built this tracker

Most rows come from a story in the Pacific Software Ventures newsroom, which reads the underlying order, filing, docket or ordinance. The source link goes to that document where one is public, and otherwise to the first source the story cites. Measures the newsroom has not covered link the government page, law firm note or local report we read, named in the row, so check those against the official record.

Status is as of the date shown, unless an update says otherwise. We add a row when the newsroom reports a new action, and we do not add rows from memory. Dollar and megawatt figures are what the companies and governments state, and we attribute them.

For a wider count of local fights, see Data Center Watch. For state legislation, see the Rockefeller Institute. To report an error or a measure we missed, send us the source document.

Cite as: Pacific Software Ventures, US Data Center Moratorium Tracker, updated November 4, 2026, https://pacificsoftwareventures.com/data-center-moratorium-tracker.

Frequently asked

Data center moratoriums, answered

Which states have a data center moratorium?
New York's Executive Order 62 pauses state environmental permits for new data centers of 50 MW or more, for up to one year. In Texas, the governor directed the state's environmental agency to pause data center permits until ERCOT finishes its review. Massachusetts, Maryland and Pennsylvania set conditions rather than a pause. Maine's legislature passed a moratorium, but the governor vetoed it.
Which cities and counties have a data center moratorium?
Among those listed here: Seattle, Denver, Indianapolis, Cleveland, Minneapolis, Charlotte and San Francisco, and Montgomery, Prince George's and Anne Arundel counties in Maryland. Many smaller towns and counties have them too, and those are not listed.
What is a data center moratorium?
A temporary stop on new data center applications or permits, usually while a government writes new rules. Terms vary, so check the source for what counts as new and what is exempt.
Is this list complete?
No. It covers the largest measures Pacific Software Ventures has reported or read, and hundreds of smaller local ones are not here. Data Center Watch, a research project that tracks local opposition, counted at least 45 US projects blocked or delayed from April through June 2026.
How current is it?
It was last updated November 4, 2026. Each row gives the date of the action and links its primary source. Measures can change quickly, so read the source before relying on a row. This page is not legal advice.
Can I reuse this data?
Yes. Download the CSV and cite Pacific Software Ventures with a link to this page. To report an error or a measure we missed, contact us with the source document.