NVIDIA’s Unstarted Data Center Leases Jump to $74 Billion
NVIDIA’s third-quarter filing, released November 17, shows the chipmaker taking on more data center real estate risk in its own name and less on behalf of others. Leases signed but not yet started rose to $74 billion, guarantees rose to $118 billion, and commitments to neoclouds fell to $32 billion with new conditions attached. PSV compared the November and August CFO commentaries line by line.
Direct answer
Direct answer to NVIDIA data center leases
NVIDIA’s data center leases that have not commenced total $74 billion as of October 25, 2026, against about $45 billion across two lease lines in August, with $63 billion falling in fiscal 2032 or later. Its maximum guarantee exposure rose from $108.5 billion to $118.0 billion. Its neocloud commitments fell from $36 billion to $32 billion and now apply only if the neocloud secures financing and NVIDIA accepts the deployed capacity.

What NVIDIA filed
NVIDIA filed a Form 8-K on November 17, 2026 under Item 2.02 with two exhibits: the press release announcing results for its third quarter of fiscal 2027, which ended October 25, 2026, and a CFO commentary. The release reports revenue of $115.8 billion, up 103% from a year earlier, of which Data Center revenue was $107.6 billion, up 110%. Colette Kress, who is interim CEO and remains CFO after Jensen Huang’s November 11 resignation, is quoted saying “Our momentum is real.” The company guides fourth-quarter revenue to $130.0 billion, plus or minus 3%, for a quarter that includes an extra week. Those are the company’s own figures and outlook, not PSV findings.
The real estate is in the CFO commentary. It says NVIDIA’s cloud service agreements and data center lease commitments together reached $102 billion, up from $74 billion last quarter. In its commitments table, “data center leases not commenced” total $74 billion, of which $63 billion falls in fiscal 2032 and after. The commentary says those leases have terms up to twenty years, have not commenced, are expected to commence between the fourth quarter of fiscal 2027 and fiscal 2033, and that NVIDIA “may assign some of these leases to third parties in the future.” A separate table of “neocloud agreements,” formerly called AI cloud agreements, totals $32 billion. Maximum gross exposure under guarantees is $118.0 billion: $105.0 billion of credit support for SB Energy’s PORTS-Pike campus in Ohio, $9.5 billion of power and systems credit support, and $3.5 billion of land, power and shell guarantees for neoclouds. NVIDIA says it has made no payments under any guarantee.
Why a CRE operator should care
NVIDIA is becoming a data center tenant at a scale that only hyperscalers reached before, and it is signing for buildings years ahead. The August commentary, filed with NVIDIA’s second-quarter 8-K, split leases into two lines: $25 billion of its own data center leases not commenced, and $20 billion of leases “for third party” that it expected to reassign. The $74 billion of cloud and lease commitments NVIDIA now gives for last quarter equals those two lines plus $29 billion of cloud agreements, so PSV reads the November lease line as combining both lease categories; the commentary does not say so in those words. On that reading, unstarted leases rose from about $45 billion to $74 billion in one quarter, about 64%, on PSV’s arithmetic. About 85% of the new total falls in fiscal 2032 or later.
The second change runs the other way. In August, NVIDIA’s $36 billion of AI cloud agreements carried no stated conditions. In November, the renamed neocloud agreements total $32 billion and “take effect only if the neoclouds secure financing to purchase the data center infrastructure products and the related compute capacity is deployed, made operational, and accepted by us,” and “certain commitments could be reduced or eliminated.” The PORTS-Pike guarantee is now described building by building: nine buildings, each guarantee effective only when its building is ready for service, the first expected in fiscal 2029, and the August line pricing each generation of NVIDIA equipment at the site at $150 billion to $200 billion of revenue is gone. NVIDIA is putting more of its own name on leases and guarantees and tying its support for smaller operators to their own financing. That is PSV’s reading of two filings, not a statement by the company.
| Line | July 26, 2026 | October 25, 2026 |
|---|---|---|
| Data center leases not commenced (own) | $25 | $74 (single line) |
| Data center leases not commenced (for third party) | $20 | Not shown separately |
| Cloud service agreements | $29 | $28 |
| AI cloud / neocloud agreements | $36, no stated conditions | $32, conditional on neocloud financing and acceptance |
| SB Energy PORTS-Pike credit support (maximum) | $105.0 | $105.0 |
| Power and systems credit support (maximum) | Not shown | $9.5 |
| Land, power and shell guarantees for AI clouds / neoclouds (maximum) | $3.5 | $3.5 |
| Total guarantee exposure (maximum) | $108.5 | $118.0 |
The workflow PSV would run
The artifact is a quarterly tenant-commitment register for any owner, lender or developer with exposure to a technology tenant that discloses its real estate obligations in an earnings filing. Inputs: the current and prior quarter’s CFO commentary or MD&A, the commitments and guarantees notes from the 10-Q when it lands, any 8-K that files a lease or guaranty, and your own lease or term sheet with that tenant. Output: one row per obligation line, current and prior quarter side by side, the change in dollars and percent, the years in which the payments fall, every condition or contingency attached to the line in the company’s own words, and a flag wherever a line was renamed, merged, split or dropped. An assistant can extract the tables and draft the comparison; a person checks each figure against the exhibit page it came from.
The reviewer is the credit officer or head of asset management who owns the tenant relationship. The gate is any decision that leans on the tenant’s credit: an underwriting assumption, a loan sizing, a lease negotiation or a disclosure to investors does not cite the register until the reviewer has confirmed the figures and written down how renamed or merged lines were mapped. Here that means recording that the November lease line is read, by PSV, as the August own-lease and third-party-lease lines combined, and revisiting it when the 10-Q explains the change.
What stays human, and what the filing does not settle
The operator read
Finish with the judgment call.
The reported facts are above. Enter your email for PSV's operator conclusion and a year of access to every newsroom brief.
Free. No card. Privacy policy.
by PSVLiveBuild the workflow behind this analysis. Train with the operators doing it.
Real deal files, live builds, and production-ready CRE AI workflows inside the CRE AI Institute.
Clear answers
Common questions about NVIDIA data center leases
How much does NVIDIA owe on data center leases?
NVIDIA’s CFO commentary for the quarter ended October 25, 2026 lists $74 billion of data center leases that have not commenced, with $63 billion of the payments in fiscal 2032 and later. The leases run up to twenty years and are expected to start between the fourth quarter of fiscal 2027 and fiscal 2033. NVIDIA says it may assign some of them to third parties.
Did NVIDIA reduce its support for neocloud data centers?
Its neocloud agreements fell from $36 billion in August to $32 billion in November and now carry stated conditions: they take effect only if the neocloud secures financing to buy the infrastructure and NVIDIA accepts the deployed capacity, and some could be reduced or eliminated. Over the same quarter its own leases and its guarantee exposure both rose.
What is NVIDIA’s data center guarantee exposure?
Maximum gross exposure was $118.0 billion as of October 25, 2026: $105.0 billion of credit support for SB Energy’s PORTS-Pike campus in Ohio, $9.5 billion of power and systems credit support, and $3.5 billion of land, power and shell guarantees for neoclouds. NVIDIA says it has made no payments under any of them, and the PORTS-Pike guarantees start building by building, the first expected in fiscal 2029.
Primary source record
These records support the reported facts in this brief. PSV’s CRE workflow interpretation and test plan are original analysis.
- NVIDIA Corporation, Form 8-K (Items 2.02, 9.01) filed November 17, 2026, Exhibit 99.1 (press release: results for the third quarter of fiscal 2027)
- NVIDIA Corporation, CFO Commentary on Third Quarter Fiscal 2027 Results (Exhibit 99.2 to the November 17, 2026 Form 8-K)
- NVIDIA Corporation, CFO Commentary on Second Quarter Fiscal 2027 Results (Exhibit 99.2 to the August 26, 2026 Form 8-K)
- Lead image: Xpda, “Google Mayes County P0004991a,” Wikimedia Commons, CC BY-SA 4.0
Topics
Track every data center moratorium and large-load rule we have reported, with sources: US data center moratorium tracker.
Related PSV analysis
CRE CAPITAL NEWS
NVIDIA Backstopped a 20-Year Lease. CRE Has a Name for That.
NVIDIA filed a Form 8-K on August 17 disclosing multiple residual value guaranties behind leases covering approximately 4.25 gigawatts of IT load at the PORTS Technology Campus in Pike County, Ohio. SB Energy will build, own and operate the campus, an affiliate of OpenAI Group PBC is the tenant on a 20-year lease, and NVIDIA’s aggregate payment obligation is cumulatively capped at $105 billion.
CRE AI NEWS
Jensen Huang Resigns: What It Means for NVIDIA-Backed Leases
NVIDIA’s board accepted Jensen Huang’s resignation as president, CEO and director on November 11, effective immediately, and named CFO Colette Kress interim CEO and longtime director Harvey Jones its first chair. The company’s filing gives no reason. For real estate, the question is what happens to the leases and financing NVIDIA has stood behind.
CRE CAPITAL NEWS
NVIDIA’s $500B: Compute Joins the Real Asset Stack
NVIDIA said on August 10 that it signed memorandums of understanding with Apollo, BlackRock, Blackstone, Brookfield, Goldman Sachs and KKR to establish independent compute financing platforms and mobilize over $500 billion of third-party capital. Read the About sections of that same release and the CRE fact is already on the page: three of the six describe real estate as a core business, and one of them calls itself the world’s largest alternative asset manager.
Related guides
Cornerstone PSV guides on the workflows in this article.
The CRE AI Data & Security Audit
The five-pass audit a CRE firm runs on its own document estate before connecting an assistant: folder access, document provenance, and the approval bands.
Read the guideWhat is CRE AI?
The definitional guide to commercial real estate AI: the core workflows, how it differs from a chatbot, and how to learn it.
Read the guide
by PSVLiveYou read the operator view. Now learn to run the workflow.
The AI MBA for commercial real estate: the workflows these briefs describe, taught end to end on real deal files, with live builds and a community of CRE operators.