SoftBank Takes a $3.7 Billion Loss on Data Center Power Gear

SoftBank Group says a subsidiary paid $9.5 billion to reserve power generation equipment for U.S. AI data centers, then revised its procurement plan and recorded a $3.7 billion loss on what it no longer needs. The charge helped push SoftBank to a ¥1.1 trillion net loss for the September quarter, and it impaired its Lordstown, Ohio plant as well.

BY EDITED BY ZED TRUONG7 MIN READ
SHARE

Direct answer

Direct answer to SoftBank data center equipment write-down

The loss is on equipment, not on a campus: SoftBank says it is completely unrelated to the PORTS-Pike project in Ohio, and the remaining $6.6 billion of prepayments stays allocated to PORTS-Pike and other projects. For real estate, the lesson is that power equipment reserved ahead of a site is speculative capital. Of $9.5 billion paid, $2.9 billion was non-refundable and is gone, and another $0.9 billion went to contract changes.

A long, low cream-colored factory building seen across a snowy field from behind a concrete highway barrier, with rows of rooftop exhaust stacks, utility poles and traffic signals in front, and a large dark panel on the wall reading Ride With Lordstown under an overcast sky
IMAGE: JOSEPH ZADEH / CC BY-SA 4.0The former General Motors Lordstown plant in Lordstown, Ohio, under Lordstown Motors signage in February 2022. SoftBank’s report records a ¥72.5 billion impairment on buildings and other property it acquired in Lordstown to make data center equipment; 2025 reports tied that purchase to this plant, which SoftBank’s filing does not name. Image: Joseph Zadeh / CC BY-SA 4.0.

What SoftBank reported

SoftBank Group Corp. released results for the six months ended September 30, 2026 on November 10. Its consolidated financial report says Silver Bands 7 LLC (SB7), a subsidiary in which SoftBank and its second Vision Fund have invested, entered into manufacturing capacity reservation agreements, equipment purchase contracts and other arrangements for power generation equipment for AI data center projects in the U.S., including the PORTS-Pike Technology Campus in Pike County, Ohio. SB7’s cumulative payments from the prior fiscal year through September 30 totaled ¥1,500,886 million, or $9.48 billion. SoftBank’s earnings presentation says SB7 is a separate entity from SB Energy, the group’s data center developer.

SB7 then revised its procurement strategy, which the company attributes to the evolving requirements of its existing and planned projects. SoftBank recognized a loss of ¥597,248 million ($3.73 billion) in other gain and loss: ¥457,030 million ($2.85 billion) on non-refundable advance payments for capacity and equipment no longer in the revised plan, and ¥140,218 million ($0.88 billion) on contract modifications and settlements, for which the accounting deck says cash payments are expected from the third quarter onward. SB7 also became entitled to rebates of up to $2.1 billion over ten years on future equipment purchases, subject to conditions, which SoftBank did not book as an asset. Separately, SoftBank recorded a ¥72,543 million impairment on property, plant and equipment, including buildings, it acquired in Lordstown, Ohio to establish a manufacturing facility for data center equipment, after reassessing the facility’s intended use and future plans.

Why a CRE operator should care

The earnings presentation charts net income attributable to owners by quarter, and the September quarter is the first loss in the six quarters shown: ¥1,115.3 billion, which SoftBank translates as $7.0 billion. The equipment charge is a pre-tax item, so it is not a straight share of that figure, but it is roughly half its size. SoftBank’s presentation describes the $9.5 billion as bridge investments made in advance to secure power equipment in anticipation of shortages, which it expects to recoup through project financing. In other words, the group paid for turbines and related gear before the projects that would use them were all fixed, and about 30 percent of what it paid is now written off (PSV arithmetic: $2.9 billion of $9.5 billion).

That is a real estate problem because power is what separates an AI data center site from farmland. Developers and landlords have been reserving long-lead power equipment early so that a site can promise energization dates to a tenant. SoftBank’s filing shows what that reservation costs when plans move: the non-refundable share is lost, changing a contract has its own price, and the rebate it negotiated ties future purchases to the same suppliers. The same report shows the group still expanding, with an 8.0 GW-IT PORTS-Pike campus preparing for construction under a 20-year OpenAI lease and a 753 MW-IT Milam County, Texas campus under construction, so this reads as a reallocation, not a retreat.

SoftBank’s power equipment and Lordstown charges, six months ended September 30, 2026, from SoftBank Group’s consolidated financial report and accounting presentation (dollar figures as SoftBank translated them, except where PSV converted)
ItemAmountWhat the record says
Cumulative payments by SB7 for power generation equipment$9.5 billion (¥1,500.9 billion)From the prior fiscal year through September 30, 2026
Loss on non-refundable advance payments$2.9 billion (¥457.0 billion)Equipment and capacity no longer in the revised plan
Loss on contract modifications and settlements$0.9 billion (¥140.2 billion)Cash payments expected from the third quarter onward
Prepayments kept$6.6 billionAllocated to the PORTS-Pike power generation project and others
Rebates on future equipment purchasesUp to $2.1 billion over 10 yearsConditional; not recognized as an asset
Lordstown, Ohio impairment¥72.5 billion, about $450 million (PSV conversion at ¥160.12)Buildings and other property acquired to make data center equipment

The workflow PSV would run

The artifact this story calls for is a power equipment commitments register, kept by whoever controls a development pipeline. Inputs: every capacity reservation agreement, equipment purchase contract and payment schedule; the refundability, cancellation and modification terms in each; and the energization date each project actually needs. Output: one row per reserved slot, matched to a named site and a need date, with the cash paid, the non-refundable share and the cost to exit shown in separate columns. An assistant can draft the extraction from the contracts and flag any slot with no matched project, but every term it pulls is checked against the signed document.

The reviewer is the head of development finance with procurement counsel, and the approval gate is simple: no new reservation payment is approved unless the register shows a matched project and a reviewed refundability term. On the buy side the same register becomes a diligence request. A buyer or lender on a powered site should ask the seller for its equipment rows and treat anything non-refundable and unmatched as the seller’s risk, not the site’s value.

What stays human, and what the record does not settle

The operator read

Finish with the judgment call.

The reported facts are above. Enter your email for PSV's operator conclusion and a year of access to every newsroom brief.

THIS ARTICLEALL PSV BRIEFSNO CARD REQUIRED
Send the operator read

Free. No card. Privacy policy. Unsubscribe anytime.

Dispatch the read

Keep the operator view in your deal room.

CRE AI Instituteby PSVLive

Build the workflow behind this analysis. Train with the operators doing it.

Real deal files, live builds, and production-ready CRE AI workflows inside the CRE AI Institute.

Clear answers

Common questions about SoftBank data center equipment write-down

Why did SoftBank take a $3.7 billion loss on data center equipment?

SoftBank’s report for the six months ended September 30, 2026 says its subsidiary Silver Bands 7 paid $9.48 billion to reserve manufacturing capacity and buy power generation equipment for U.S. AI data center projects, then revised its procurement plan for its existing and planned projects. SoftBank recorded a ¥597.2 billion ($3.73 billion) loss: $2.85 billion on non-refundable advance payments and $0.88 billion on contract modifications and settlements.

Is SoftBank’s equipment loss related to the PORTS-Pike data center in Ohio?

SoftBank says no. Its earnings presentation states that the $3.7 billion loss is completely unrelated to PORTS-Pike, and that the remaining $6.6 billion of prepayments is allocated to the PORTS-Pike power generation project and others. That is the company’s statement; it has not named the projects whose equipment was cancelled.

How much did SoftBank lose in the September 2026 quarter?

SoftBank’s earnings presentation shows net income attributable to owners of the parent of minus ¥1,115.3 billion for the quarter ended September 30, 2026, which it translates as a $7.0 billion loss. For the six months, the net loss was ¥768.0 billion, or $4.8 billion. The power equipment charge and a ¥321.9 billion derivative loss on Intel-backed prepaid forward contracts were among the items SoftBank highlighted.

Primary source record

These records support the reported facts in this brief. PSV’s CRE workflow interpretation and test plan are original analysis.

Topics

CRE CAPITAL NEWSSoftBank data center equipment write-downSoftBank $3.7 billion loss power generation equipmentSilver Bands 7 power equipment advance paymentsSoftBank Q2 FY2026 net loss data centerSoftBank Lordstown impairmentdata center turbine transformer reservation deposits

Track every data center moratorium and large-load rule we have reported, with sources: US data center moratorium tracker.

CRE CAPITAL NEWS

SB Energy’s IPO Filing Put OpenAI’s Data Center Leases on the Record

SB Energy, SoftBank’s AI data center and power developer, filed its S-1 on September 1 and added the leases themselves on September 4. It reports about $430 billion of data center backlog across 8.8 GW-IT of signed leases and no data center capacity in operation, with OpenAI the tenant on all but 50 MW. PSV read the prospectus and the filed leases the way a lender would.

Read SB Energy IPO

CRE AI NEWS

Brookfield’s Q3: Real Estate Raised $900 Million, Then Bought Into Data Centers

Brookfield Asset Management furnished its third quarter results to the SEC on November 6: $25 billion raised in the quarter and $123 billion year to date. Its real estate strategies raised $900 million of that, about 3.6 percent, and the one new real estate commitment it highlighted was a stake in a U.S. hyperscale data center developer.

Read Brookfield Q3 2026 results data center AI infrastructure

CRE AI NEWS

Riot Leases All of Corsicana to Anthropic: 910 MW of Powered Land, No Building

Riot Platforms signed a 15-year triple-net powered land lease for its entire 910 critical IT megawatt Corsicana, Texas campus, at $130 per kilowatt a month escalating 3 percent a year. Riot’s release calls the tenant a leading frontier AI lab; its quarterly report on Form 10-Q names Anthropic PBC.

Read Riot Platforms Corsicana lease Anthropic

Cornerstone PSV guides on the workflows in this article.

Back to the CRE AI Newsroom
CRE AI Instituteby PSVLive

You read the operator view. Now learn to run the workflow.

The AI MBA for commercial real estate: the workflows these briefs describe, taught end to end on real deal files, with live builds and a community of CRE operators.