Riot Leases All of Corsicana to Anthropic: 910 MW of Powered Land, No Building

Riot Platforms signed a 15-year triple-net powered land lease for its entire 910 critical IT megawatt Corsicana, Texas campus, at $130 per kilowatt a month escalating 3 percent a year. Riot’s release calls the tenant a leading frontier AI lab; its quarterly report on Form 10-Q names Anthropic PBC.

BY EDITED BY ZED TRUONG8 MIN READ
SHARE

Direct answer

Direct answer to Riot Platforms Corsicana lease Anthropic

This is a data center lease with no data center in it. Riot delivers land, high and medium voltage power and powered pads; the tenant buys, installs, owns and runs the compute modules and pays every operating cost, and Riot says the project costs about $6 million per megawatt, roughly half a Tier 3 build. The real underwriting question is the fallback clause that turns up to $3.64 billion of reimbursements into rent credits at 12 percent.

Aerial view of Riot’s Corsicana, Texas campus: two long white-roofed halls side by side with rows of equipment units along both walls, an electrical substation with steel gantries and a white trailer in the foreground, graded dirt yards with stacked materials, and pasture, trees and a pond beyond the site
IMAGE: RIOT PLATFORMSRiot’s Corsicana campus in Navarro County, Texas, from the photograph on Riot’s own Corsicana location page, which does not date it. The halls shown are Riot’s existing facilities; under the lease effective November 4, 2026, Riot delivers land, power infrastructure and powered pads across the 910 megawatt campus, and the tenant brings its own compute modules. Image: Riot Platforms.

What Riot filed

Riot Platforms, Inc. (Nasdaq: RIOT) announced on November 4, 2026, with its third quarter results, that it had signed a 15-year triple-net powered land lease for the entirety of its Corsicana campus in Navarro County, Texas, covering 910 megawatts of critical IT capacity on a contiguous 332-acre parcel. The release, furnished to the SEC the same day as Exhibit 99.1 to a Form 8-K, puts the total contract value at approximately $28 billion and average annual rent at approximately $1.8 billion over the initial term, including escalators, and approximately $54 billion if the tenant exercises both five-year extension options. Riot estimates an NOI margin of about 99 percent under the triple-net structure. Chief executive Jason Les called it “the largest lease in Riot’s history.” The release names the tenant only as “a leading Frontier AI Lab,” the same lab that signed the 191 megawatt Rockdale lease in August. Those are the company’s figures and characterizations, not PSV findings.

Riot’s quarterly report on Form 10-Q, filed November 4, carries the contract terms. It says Riot Corsicana, LLC entered the lease on October 28, 2026 “with Anthropic PBC (the ‘Frontier AI Lab’),” and that it became effective and binding on November 4 after Riot’s board approved it and the company’s third-party consultants approved the technical specifications. Because the report uses the same defined term for the Rockdale tenant, the filed record now identifies Anthropic at both campuses. Capacity arrives in 40 blocks across three phases: 400 megawatts with the first block targeted for June 28, 2027 and the full phase for September 11, 2027; 200 megawatts from December 24, 2027 to January 28, 2028; and 310 megawatts on July 30, 2028. The initial term runs to the month of the 15th anniversary of Phase 3. Base rent is $130.0 per kilowatt of critical IT capacity per month for each delivered block, escalating 3 percent a year, and the tenant also bears taxes, insurance, site expenses and the electricity it uses. Riot builds and maintains the power and site infrastructure at its own cost and will reimburse the tenant for data center modules up to $4.0 million per megawatt achieved, subject to obtaining financing on market terms; if it cannot, it provides rent credits that amortize that amount plus 12 percent annual interest over the rest of the initial term.

Why a CRE operator should care

The structure is the news. In this lease the landlord sells interconnection, substations and graded, powered pads, and the tenant brings the building, as factory-made modules it owns. Riot says total capital is about $6 million per IT megawatt, or $5.5 billion, which it describes as roughly half the capital intensity of a typical Tier 3 build, and it puts the unlevered yield on cost at about 33 percent. The arithmetic holds on Riot’s own numbers: $1.8 billion of average rent over $5.5 billion computes to 32.7 percent. PSV’s own run of the filed terms comes out close to the release. At full capacity, $130 per kilowatt a month on 910,000 kilowatts computes to about $1.42 billion of base rent in the first year, and averaging 15 years of 3 percent escalation computes to about $1.76 billion a year, or roughly $26.4 billion over 15 years. Rent on the first two phases before Phase 3 starts the 15-year clock accounts for much of the gap to Riot’s $28 billion; the filed terms do not say exactly when each block’s escalator starts, so PSV does not reconcile the last few hundred million dollars.

Set it next to Riot’s other lease with the same tenant and the two products separate cleanly. The comparison below uses only Riot’s published figures, and the per-kilowatt and per-megawatt rates are PSV arithmetic on them.

Riot’s two leases with the same frontier AI lab, from Riot’s filings (per-unit rates are PSV arithmetic)
TermRockdale (signed August 2026)Corsicana (effective November 4, 2026)
ProductBuild-to-suit Tier 3 data centerTriple-net powered land: land, power infrastructure, powered pads
Critical IT capacity191 MW910 MW
Initial term20 years, through June 204815 years from Phase 3 commencement
RentAbout $457 million average annual revenue, or roughly $199 per kW a month$130 per kW a month at start, up 3 percent a year; about $1.8 billion average annual rent
Riot capital$2.1 to $2.3 billion, or roughly $11 to $12 million per MW, excluding tenant fit-outAbout $5.5 billion, or $6 million per MW, including up to $4 million per MW reimbursed for tenant modules
Who owns the compute buildingRiot builds itTenant procures, installs, owns and operates the modules

The workflow PSV would run

Anyone underwriting a powered land deal, whether as landlord, lender or buyer of the paper, should build the rent model from the lease clauses, not the press release, because the two describe the fallback differently. The release says that if project debt is not available on comparable terms, the tenant funds the reimbursements and recovers them as a credit against rent. The 10-Q adds the price: the credits amortize the amount plus 12 percent a year. Inputs for the model: the block delivery schedule, the rent commencement clause for each pad, the base rate and escalator, the reimbursement cap and its financing condition, the credit interest rate, the triple-net cost list, and the utility interconnection agreement. Output: a monthly cash rent schedule under both reimbursement paths, every line citing the clause it came from. On PSV’s arithmetic, amortizing the full $3.64 billion at 12 percent over 15 years computes to about $534 million a year, roughly 30 percent of average rent, so the path chosen moves cash rent more than any other single term.

The reviewer is the deal team’s real estate counsel with the asset manager who owns the power schedule, and the approval gate is that no rent forecast leaves the building until counsel has tied each line to the executed lease. An assistant can draft the schedule and flag where the record is silent; it should not decide which financing path is likely or what the tenant’s credit is worth. Two things to design against: treating the 99 percent NOI margin as cash yield when rent credits may be netting against it, and assuming the campus is free of its current use. Riot’s 10-Q says Corsicana is equipped today for roughly 400 megawatts of bitcoin mining, and the filings PSV read do not say when that ends.

What stays human, and what the record does not settle

The operator read

Finish with the judgment call.

The reported facts are above. Enter your email for PSV's operator conclusion and a year of access to every newsroom brief.

THIS ARTICLEALL PSV BRIEFSNO CARD REQUIRED
Send the operator read

Free. No card. Privacy policy. Unsubscribe anytime.

Dispatch the read

Keep the operator view in your deal room.

CRE AI Instituteby PSVLive

Build the workflow behind this analysis. Train with the operators doing it.

Real deal files, live builds, and production-ready CRE AI workflows inside the CRE AI Institute.

Clear answers

Common questions about Riot Platforms Corsicana lease Anthropic

Who is the tenant in Riot’s Corsicana data center lease?

Riot’s November 4, 2026 release calls the tenant “a leading Frontier AI Lab.” Its quarterly report on Form 10-Q, filed the same day, says Riot Corsicana, LLC entered the lease on October 28, 2026 with Anthropic PBC, defined in the filing as the Frontier AI Lab, and that the lease became effective on November 4. The 10-Q uses the same defined term for the tenant of Riot’s 191 megawatt Rockdale lease signed in August.

What is a powered land lease for a data center?

In Riot’s Corsicana structure, the landlord delivers land, high and medium voltage power infrastructure and powered pads, and keeps owning and maintaining the power infrastructure. The tenant procures, installs, owns and operates modular compute on the pads and pays taxes, insurance, site costs and its electricity. Riot puts the capital at about $6 million per IT megawatt, which it says is roughly half a typical Tier 3 build, and rent is payable on the full 910 megawatts regardless of utilization.

How much is Riot’s Corsicana lease worth?

Riot puts total contract value at approximately $28 billion over the 15-year initial term and about $54 billion if both five-year extensions are exercised, with average annual rent of about $1.8 billion. The 10-Q sets base rent at $130 per kilowatt of critical IT capacity per month, escalating 3 percent a year. At full capacity that computes to about $1.42 billion in the first year, which is PSV arithmetic, not a Riot figure. Up to $3.64 billion of module reimbursements could become rent credits at 12 percent interest if Riot cannot finance them.

Primary source record

These records support the reported facts in this brief. PSV’s CRE workflow interpretation and test plan are original analysis.

Topics

CRE AI NEWSRiot Platforms Corsicana lease Anthropic910 MW powered land lease data centertriple-net powered land lease AI labdata center rent per kW per month 2026Riot Corsicana $28 billion leasepowered shell vs Tier 3 data center capital cost

Track every data center moratorium and large-load rule we have reported, with sources: US data center moratorium tracker.

CRE CAPITAL NEWS

Riot’s $573M Bridge Matures Before the Rent Starts

Riot Platforms filed a Form 8-K on August 14 reporting that a project subsidiary closed a senior secured delayed-draw term loan of up to $573.0 million, with Morgan Stanley Senior Funding as administrative agent, to buy long-lead equipment for the 191 critical IT megawatt data center at its Rockdale campus. The loans mature December 31, 2026. The first megawatts are not due to energize until December 2027.

Read Riot Platforms Rockdale data center credit facility

CRE AI NEWS

An Unnamed AI Lab Commits to Lease Cipher’s Barber Lake Data Center From Year 11

Cipher Digital said on September 25, 2026 that a leading AI lab it does not name made a binding commitment to lease its Barber Lake data center in Colorado City, Texas for ten years after Fluidstack’s ten-year lease ends. Cipher puts the added contracted revenue at about $5.2 billion. The same filing moves delivery into phases and sets who pays for cost overruns.

Read Cipher Digital Barber Lake lease 20 years

CRE POLICY NEWS

Texas Elects a Governor Who Promised a Data Center Moratorium

Democrat Gina Hinojosa won the Texas governor’s race on November 3 after a campaign that called for an immediate moratorium on new data centers until the Legislature passes protections. Governor Greg Abbott’s own audit pause runs until ERCOT reports on December 10. Hinojosa takes office in January, and the moratorium she promised has no published text.

Read Texas governor data center moratorium

Cornerstone PSV guides on the workflows in this article.

Back to the CRE AI Newsroom
CRE AI Instituteby PSVLive

You read the operator view. Now learn to run the workflow.

The AI MBA for commercial real estate: the workflows these briefs describe, taught end to end on real deal files, with live builds and a community of CRE operators.