Applied Digital Signs 150 MW, 18-Year Lease. No Campus Is Named.

Applied Digital said on November 23 that it signed an 18-year lease with an investment-grade hyperscaler for 150 MW, worth about $5.4 billion over the base term. The release doesn’t name the tenant or the campus. On PSV’s arithmetic the rent runs about 21 percent above the company’s June lease. The same morning it closed a $300 million, 364-day bridge loan for its Louisiana campus.

BY EDITED BY ZED TRUONG7 MIN READ
SHARE

Direct answer

Direct answer to Applied Digital 150 MW lease

The headline number is a base-term total, so turn it into rent before you compare it with anything. It computes to about $2.0 million per megawatt a year, or roughly $167 per kilowatt a month, against about $138 on the June lease. Delivery starts in the first half of 2028 and depends on utility and regulatory approvals. Until a filing shows the lease, treat the terms as a company claim.

A long, low white data center building with a band of dark louvered panels along its upper wall, seen across a dry golden field with a wire fence and scattered pine trees in front of it, under a heavy blue-gray sky.
IMAGE: GARY HALVORSON, OREGON STATE ARCHIVES / CC BY 4.0A Facebook data center west of Prineville, Oregon, off Highway 126, photographed for the Oregon State Archives. It isn’t an Applied Digital building, and Applied Digital’s November 23, 2026 release doesn’t say where the newly leased 150 MW will be built. The photograph shows the building type the story is about: a single-tenant hyperscale data hall on rural land. Image: Gary Halvorson, Oregon State Archives / CC BY 4.0.

What Applied Digital announced

On November 23, 2026, Applied Digital (Nasdaq: APLD), the Dallas data center developer, said it had entered into a new 18-year lease with what it calls a tier-one investment-grade hyperscaler for 150 MW of critical IT capacity. The company says the lease provides approximately $5.4 billion of base-term contracted revenue, or approximately $12.7 billion if every renewal option is exercised over a 33-year total term. It says the lease has “improved commercial terms over our prior leases, including higher pricing,” and that delivery should begin in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals. The release names neither the tenant nor the campus. As of the morning of November 24, PSV found no Form 8-K on EDGAR for the lease, so the lease itself isn’t public.

Fifteen minutes earlier, the company announced the closing of a $300 million senior secured bridge facility led by a lender it describes only as a leading global financial institution. It’s a delayed draw term loan with a 364-day maturity, priced at SOFR plus 300 basis points, secured by the project’s assets and prepayable without premium. The money is for construction of Delta Forge 1, the company’s campus in Louisiana. Draws depend on conditions that include construction milestones, lender consents, financial covenants and state commission approval of electrical rates, and the company says it expects to seek more financing to finish the campus. With the new lease, Applied Digital puts its portfolio at more than $41 billion of base-term contracted revenue, about $100 billion with every renewal, on over 1.6 GW of contracted critical IT load. It says about 75 percent of the base-term revenue is attributable to investment-grade tenants. Chief Financial Officer Saidal Mohmand said the build will be funded with equity already in from the balance sheet and through a $5 billion programmatic equity partnership with Macquarie Asset Management, followed by project financing.

Why a CRE operator should care

A $5.4 billion lease tells you about as much as a $40 million office lease does before you know the square footage and the term. So do the division. $5.4 billion over 18 years is $300 million a year. Across 150 MW that computes to about $2.0 million per megawatt a year, or roughly $167 per kilowatt a month. The company’s last lease, signed June 5 at Delta Forge 2, was 210 MW for approximately 15 years and approximately $5.2 billion, according to its Form 10-Q filed October 7. That computes to about $1.65 million per megawatt a year, or roughly $138 per kilowatt a month. On those averages the new rent is about 21 percent higher. That’s PSV arithmetic on rounded company figures. It can’t see escalators, free rent, the delivery ramp or what the landlord builds for the money, because none of that is disclosed.

The renewal number needs the same treatment. The release implies $7.3 billion for the 15 years after the base term, which computes to about $487 million a year, roughly 1.6 times the base-term average. That’s rent the tenant can choose not to pay, and the company’s own risk language says it won’t recognize further revenue from a customer that doesn’t renew. Would you underwrite an office tower on its option rent? The megawatts need a reconciliation too. The October 10-Q put aggregate contracted critical IT load at 1,410 MW. Add 150 and you get 1,560 MW, which is short of “over 1.6 GW.” The building capacities listed in that same filing compute to 1,510 MW, which would make 1,660. Neither record explains the gap. The dollars do tie: the company reported about $36 billion in October, and $5.4 billion more is about $41.4 billion.

The workflow PSV would run

Build one lease normalization sheet for powered-shell and build-to-suit data center comps. Inputs are the two November 23 releases, the lease note in the October 10-Q, the Form 8-K if one is filed, and the lease or term sheet from your own deal. The model reads each record and fills one row per lease: megawatts, base term, base-term revenue, renewal years, renewal revenue, delivery window, stated conditions, and the record each figure came from. Rent per megawatt a year and per kilowatt a month are formulas in the sheet that anyone can click on. The model doesn’t do that arithmetic in its head.

The reviewer is the acquisitions or capital markets lead. The rule is that no row goes into an IC memo, a BOV or a lender package until a person has matched every input to its record and tagged the row as filed or as a company claim. A second tab is a dates calendar for the landlord’s side of the deal. For Applied Digital it would hold the bridge loan’s 364-day maturity, the project financings the company expects in the first calendar quarter of 2027 for Delta Forge 1 and Polaris Forge 3 and in the second quarter for Delta Forge 2, the state commission’s rate decision, and delivery in the first half of 2028. Each date gets an owner and a source link.

What should remain human-owned

The operator read

Finish with the judgment call.

The reported facts are above. Enter your email for PSV's operator conclusion and a year of access to every newsroom brief.

THIS ARTICLEALL PSV BRIEFSNO CARD REQUIRED
Send the operator read

Free. No card. Privacy policy.

Dispatch the read

Keep the operator view in your deal room.

CRE AI Instituteby PSVLive

Build the workflow behind this analysis. Train with the operators doing it.

Real deal files, live builds, and production-ready CRE AI workflows inside the CRE AI Institute.

Clear answers

Common questions about Applied Digital 150 MW lease

How much is Applied Digital’s new 150 MW lease worth?

Applied Digital’s November 23, 2026 release says the 18-year lease provides approximately $5.4 billion of base-term contracted revenue, or approximately $12.7 billion if every renewal option is exercised over a 33-year total term. On PSV’s arithmetic the base term computes to $300 million a year, about $2.0 million per megawatt a year, or roughly $167 per kilowatt a month. Those are averages on rounded company figures. The release doesn’t disclose escalators, concessions or the landlord’s scope.

Who is the tenant on Applied Digital’s 150 MW lease, and where is the campus?

The release names neither. It describes the tenant as a tier-one investment-grade hyperscaler and gives no campus or state for the 150 MW. Delivery is expected to begin in the first half of calendar 2028, subject to development milestones, utility arrangements and regulatory approvals. As of the morning of November 24, 2026, PSV found no Form 8-K on EDGAR for the lease.

What is Applied Digital’s $300 million bridge facility for?

The company says the facility, announced November 23, 2026, funds continued development and construction of Delta Forge 1, its campus in Louisiana. It’s a $300 million senior secured delayed draw term loan with a 364-day maturity at SOFR plus 300 basis points, secured by the project’s assets. Draws depend on conditions that include construction milestones, lender consents, financial covenants and state commission approval of electrical rates. The lender isn’t named.

Primary source record

These records support the reported facts in this brief. PSV’s CRE workflow interpretation and test plan are original analysis.

Topics

CRE CAPITAL NEWSApplied Digital 150 MW leaseApplied Digital 18-year hyperscaler leasedata center rent per kW per monthApplied Digital $300 million bridge facility Delta Forge 1Applied Digital contracted revenue $41 billion

Track every data center moratorium and large-load rule we have reported, with sources: US data center moratorium tracker.

CRE AI NEWS

Applied Digital Signs a 1,200 MW Gas Power Deal With a Company Its CEO Runs

Applied Digital’s Form 10-Q, filed October 7, discloses a 15-year power purchase agreement signed October 4 for capacity and energy from a roughly 1,200 megawatt gas-fired plant that Base Electron plans to build in Center, North Dakota, for the Polaris Forge 3 data center campus. The filing says Base Electron is owned and managed by Applied Digital officers and directors, and that Applied Digital’s chief executive is also Base Electron’s.

Read Applied Digital Base Electron power purchase agreement

CRE CAPITAL NEWS

Hut 8’s $9.8B Beacon Point Lease: The CRE Read on a Fully Leased AI Campus

Hut 8 said on July 20 it signed a second 15-year lease at its Beacon Point campus in Nueces County, Texas, a 352 megawatt deal with a base-term contract value of $9.8 billion. The lease fully commercializes the one-gigawatt campus, doubling the tenant’s contracted capacity to 704 megawatts. For real estate, the detail that matters is the structure: a triple-net, take-or-pay lease to a single investment-grade tenant, energizing in 2027.

Read Hut 8 Beacon Point data center lease commercial real estate

CRE AI NEWS

An Unnamed AI Lab Commits to Lease Cipher’s Barber Lake Data Center From Year 11

Cipher Digital said on September 25, 2026 that a leading AI lab it does not name made a binding commitment to lease its Barber Lake data center in Colorado City, Texas for ten years after Fluidstack’s ten-year lease ends. Cipher puts the added contracted revenue at about $5.2 billion. The same filing moves delivery into phases and sets who pays for cost overruns.

Read Cipher Digital Barber Lake lease 20 years

Cornerstone PSV guides on the workflows in this article.

Back to the CRE AI Newsroom
CRE AI Instituteby PSVLive

You read the operator view. Now learn to run the workflow.

The AI MBA for commercial real estate: the workflows these briefs describe, taught end to end on real deal files, with live builds and a community of CRE operators.