CRE POLICY NEWS
Federal Land Is Becoming a Data Center Land Market
The Department of Energy has now picked developers for AI data center campuses on three former nuclear sites, and the Bureau of Land Management approved its first data center on public land in June. A November 15 Bisnow tally counts at least 17 parcels and 19,200 acres under federal consideration. The agency records show how much of that is actually approved.
Direct answer
Direct answer to data centers on federal land
Less than the headlines suggest. DOE records describe a lease to an SB Energy affiliate at Portsmouth, Ohio, a Brookfield campus on about 785 leased acres at Paducah, Kentucky that still needs a state power approval, and a Savannah River selection that NNSA says is not a final lease. BLM’s one approval, an 88.5-acre data center near Boulder City, Nevada, relied on a 2023 solar review and is under appeal.

What the agencies have actually done
The Department of Energy identified 16 federal sites in April 2025 that could host AI data centers and their power, and on July 24, 2025 it selected four to invite private partners: Idaho National Laboratory, the Oak Ridge Reservation, the Paducah Gaseous Diffusion Plant and the Savannah River Site. Three former nuclear sites now have named developers. DOE’s Portsmouth fact sheet says it is leasing federal land at the former Portsmouth Gaseous Diffusion Plant in Pike County, Ohio, to an SB Energy-affiliated entity for a data center campus, with SoftBank Group and SB Energy planning 10 gigawatts of new generation, at least 9.2 gigawatts of it natural gas, to power 10 gigawatts of data center development. At Paducah, DOE’s Office of Environmental Management said on August 4, 2026 that it selected Brookfield to develop and operate a 1.8 gigawatt AI campus on about 785 acres of leased land, with NextEra Energy building and owning 2 gigawatts of gas generation and up to 2.6 gigawatts of battery storage, in a project DOE puts at $100 billion and expects to finish in 2031. At Savannah River, NNSA said on July 20, 2026 that it selected Amentum to negotiate a phased lease for a 1 gigawatt data center with about 2 gigawatts of on-site generation, natural gas bridging to nuclear.
The Bureau of Land Management has approved one data center. Its announcement says it approved the Townsite Data Center in June 2026 on 88.5 acres of public land near the existing Townsite Solar 1 project, citing Executive Order 14318 on accelerating federal permitting of data center infrastructure. The appeal filed by the Center for Biological Diversity and the Sierra Club fills in the record: the parcel in Nevada’s Eldorado Valley was approved in 2023 as Townsite Solar 2, an up to 19 megawatt solar project with up to 35 megawatts of batteries on 76 acres; the applicant filed an amended application in November 2025; and the decision record and Determination of NEPA Adequacy posted on June 26, 2026 grant a right-of-way for a data center with a 70 megawatt battery system, a substation and backup generators, relying on the 2023 environmental assessment. Bisnow’s November 15 count of at least 17 parcels and about 19,200 acres under BLM and DOE consideration is Bisnow’s analysis of filings and trackers; PSV has not verified the total.
Why a CRE operator should care
Federal sites compete with private powered land on the thing private land lacks most. DOE says the Paducah site’s existing transmission capacity, water, fiber and available land can support large-scale AI infrastructure, and its Portsmouth fact sheet describes $4.2 billion of new transmission with AEP Ohio that SB Energy has committed to pay for, along with accelerated cleanup of the site. Every one of these deals pairs the campus with its own generation, which DOE ties to the administration’s Ratepayer Protection Pledge. For an owner of entitled, powered land in the same regions, the federal program is new supply arriving with the government as landlord and remediation as part of the bargain.
The status of each deal is less settled than its headline. NNSA states that the Savannah River selection “does not constitute a final lease award” and remains subject to negotiation, permitting and federal approvals. Paducah’s power service agreement is subject to approval by the Kentucky Public Service Commission. The records also disagree in places. Bisnow named DC Blox alongside Amentum at Savannah River, but NNSA’s release names only Amentum. BLM puts Townsite at 88.5 acres, while the appeal describes the decision as covering 81 acres of an 85-acre data center right-of-way plus about 4 acres of linear facilities. Investment, jobs and bill savings are agency and company projections, not PSV findings.
| Site | Agency | Developer | Land and power | Status in the record |
|---|---|---|---|---|
| Portsmouth, Pike County, Ohio | DOE | SB Energy affiliate (SoftBank) | 10 GW of data center development; 10 GW of new generation, at least 9.2 GW gas | Lease to SB Energy affiliate, per DOE fact sheet |
| Paducah, Kentucky | DOE | Brookfield (campus), NextEra Energy (power) | About 785 leased acres; 1.8 GW campus; 2 GW gas, up to 2.6 GW batteries | Selected; power agreement needs Kentucky PSC approval; completion expected 2031 |
| Savannah River Site, South Carolina | NNSA | Amentum | 1 GW data center; about 2 GW on-site generation | Selected to negotiate; NNSA says not a final lease award |
| Townsite, Eldorado Valley, Nevada | BLM | Townsite Solar 2 LLC | 88.5 acres per BLM; 70 MW battery per appeal filing | Approved June 2026 on the 2023 solar review; under appeal |
The workflow PSV would run
The artifact is a federal-site status sheet for every campus that competes with land a firm owns, lends on or is bidding on. Inputs: the agency announcement, the solicitation and selection notice, the lease or a statement of its status, the NEPA record (environmental assessment, finding of no significant impact or determination of NEPA adequacy, and the decision record), any appeal docket, the state utility commission filing for the power agreement, and the site’s remediation status. Output: one page per site that records whether the government has selected a partner, signed a lease or approved a right-of-way, which environmental review the approval rests on, every approval still outstanding, and every place two records disagree. An assistant can pull the figures and draft the sheet; a person checks each line against the document it came from.
The reviewer is the head of development or land acquisitions, with land-use counsel on the NEPA and appeal lines. The gate is use: nobody prices a nearby parcel, quotes a federal campus in a pitch or changes a power assumption until that reviewer has signed off on which numbers are approved and which are only proposed. The sheet is refreshed when a selection becomes a lease, when a utility commission rules, and when an appeals board acts.
What stays human, and what the record does not settle
The operator read
Finish with the judgment call.
The reported facts are above. Enter your email for PSV's operator conclusion and a year of access to every newsroom brief.
Free. No card. Privacy policy. Unsubscribe anytime.
by PSVLiveBuild the workflow behind this analysis. Train with the operators doing it.
Real deal files, live builds, and production-ready CRE AI workflows inside the CRE AI Institute.
Clear answers
Common questions about data centers on federal land
Which federal sites are being leased for AI data centers?
DOE selected four of 16 candidate sites in July 2025: Idaho National Laboratory, Oak Ridge, Paducah and Savannah River. DOE records describe a lease to an SB Energy affiliate at the former Portsmouth plant in Ohio, a Brookfield campus on about 785 leased acres at Paducah, Kentucky, and NNSA’s selection of Amentum to negotiate a phased lease for a 1 gigawatt data center at Savannah River, South Carolina.
Has BLM approved a data center on public land?
Once. BLM says it approved the Townsite Data Center in June 2026 on 88.5 acres of public land near Boulder City, Nevada, citing Executive Order 14318. The approval converted a 2023 solar right-of-way and relied on that project’s environmental assessment. The Center for Biological Diversity and the Sierra Club appealed, and local reporting says the Interior Board of Land Appeals stayed the approval on September 1, 2026.
Is the Savannah River Site data center lease final?
No. NNSA’s July 20, 2026 release says it selected Amentum to enter negotiations for a phased lease for a 1 gigawatt data center with about 2 gigawatts of on-site generation, and that the selection does not constitute a final lease award. Any agreement remains subject to negotiation, permitting, safety and security reviews and other federal approvals.
Primary source record
These records support the reported facts in this brief. PSV’s CRE workflow interpretation and test plan are original analysis.
- U.S. Department of Energy, “DOE Announces Site Selection for AI Data Center and Energy Infrastructure Development on Federal Lands,” July 24, 2025
- U.S. Department of Energy, fact sheet on the Portsmouth site AI data center partnership in Pike County, Ohio, March 2026
- DOE Office of Environmental Management, “Energy Secretary Announces New American Energy Hub at Paducah Site,” August 4, 2026
- National Nuclear Security Administration, “NNSA Selects Amentum for AI Data Center and Energy Project at Savannah River Site,” July 20, 2026
- Bureau of Land Management, “Approved Decision of Townsite Data Center”
- Center for Biological Diversity and Sierra Club, Notice of Appeal and Petition for Stay to the Interior Board of Land Appeals, Townsite Data Center Project (DOI-BLM-NV-S010-2026-0080-DNA), July 2026
- Lead image: U.S. Department of Energy, “Paducah Metals Plant,” Wikimedia Commons, public domain
Topics
Track every data center moratorium and large-load rule we have reported, with sources: US data center moratorium tracker.
Related PSV analysis
CRE CAPITAL NEWS
SB Energy’s IPO Filing Put OpenAI’s Data Center Leases on the Record
SB Energy, SoftBank’s AI data center and power developer, filed its S-1 on September 1 and added the leases themselves on September 4. It reports about $430 billion of data center backlog across 8.8 GW-IT of signed leases and no data center capacity in operation, with OpenAI the tenant on all but 50 MW. PSV read the prospectus and the filed leases the way a lender would.
CRE AI NEWS
A 400 MW Data Center Pitched for the Navy’s NAVWAR Campus
Manchester Financial Group, the Navy’s selected developer for the 70.3-acre NAVWAR Old Town Campus in San Diego, has explored a 400 megawatt data center on the site, according to public records reported on October 15. The developer says no agreements are in place. Rep. Scott Peters said on October 16 that he opposes it.
CRE AI NEWS
SpaceX Plans $74B of AI Campuses in Texas and Arizona
SpaceX said on November 12 that it plans more than $74 billion of AI supercomputing campuses: up to $24 billion on land it owns near Starbase, Texas, and roughly $50 billion in Cochise County, Arizona. The Arizona project is a 747-acre, 6 gigawatt special use application filed under another company’s name, and the county hears it on December 9.
Related guides
Cornerstone PSV guides on the workflows in this article.
Claude for Real Estate Developers
The ground-up developer field guide: site selection through IC memo, built on a real development deal.
Read the guideWhat is CRE AI?
The definitional guide to commercial real estate AI: the core workflows, how it differs from a chatbot, and how to learn it.
Read the guide
by PSVLiveYou read the operator view. Now learn to run the workflow.
The AI MBA for commercial real estate: the workflows these briefs describe, taught end to end on real deal files, with live builds and a community of CRE operators.