Prologis Q3: 5.8 GW of Data Center Power, 1.7 GW Secured

Prologis reported third quarter 2026 results on October 15. Its filed supplemental puts the data center power pipeline at 5.8 gigawatts, of which 1.7 gigawatts is secured, and data center projects under development at $2,588 million of expected investment, all leased. It started no new data centers in the quarter.

BY EDITED BY ZED TRUONG7 MIN READ
SHARE

Direct answer

Direct answer to Prologis Q3 2026 data center

Prologis, a logistics landlord, is now also a data center developer at scale, and its filings separate the power it has from the power it hopes to get. Of 5.8 gigawatts, 1.7 gigawatts is under binding utility agreements and 4.1 gigawatts is in advanced talks that Prologis says carry no guarantee. Data centers are about a third of its development book by investment.

A long, pale two-storey pier shed on wooden pilings over green-blue bay water, with a PROLOGIS sign on its gabled end under the words PIER 1, people walking along the railed apron, the Transamerica Pyramid and other downtown San Francisco towers behind it, and a ferry docked at right under a clear blue sky.
IMAGE: PI.1415926535 / CC BY-SA 3.0Pier 1 on the San Francisco waterfront, the address on the cover of Prologis’ October 15, 2026 Form 8-K, in June 2019. The building is an office pier, not a data center; the supplemental filed that day reports a 5.8 gigawatt data center power pipeline, 1.7 gigawatts of it secured. Image: Pi.1415926535 / CC BY-SA 3.0.

What Prologis filed on October 15

On October 15, 2026, Prologis, Inc. (NYSE: PLD) furnished a Form 8-K under Items 2.02 and 7.01 with two exhibits: its third quarter press release and its supplemental information for the quarter ended September 30. The company reported net earnings of $0.86 per diluted share, against $0.82 a year earlier, and Core FFO of $1.60 per diluted share, against $1.49. Chief executive Daniel S. Letter said Prologis signed 60 million square feet of leases and announced nearly $2.3 billion of transactions, and named “the build-out of the data center supply chain” alongside e-commerce and advanced manufacturing as a source of customer demand. Period-end occupancy was 95.6 percent, net effective rent change was 38.0 percent and cash same store NOI growth was 5.9 percent, all company figures. Letter also called shareholder approval of the SEGRO plc acquisition an important milestone; the deal, announced August 4, has not closed.

The data center figures sit in the supplemental, not the headline. Prologis reports a data center power pipeline of 5.8 gigawatts, made up of 1.7 gigawatts of Secured Power, including 680 megawatts under development, and 4.1 gigawatts of Advanced Stage Power. Its definitions matter more than the total. Secured Power is utility-fed capacity “subject to binding agreements with utilities.” Advanced Stage Power is capacity that is not yet secured but in advanced discussions with utilities, and the company states there is no guarantee it will become secured. Every site is owned or controlled by Prologis and subject to regulatory approvals and entitlements. The development portfolio table shows data centers at 2,182 thousand square feet and $2,588 million of total expected investment on an owned and managed basis ($2,486 million at Prologis’ share), 100 percent leased, with every project expected to complete in 2027 or later.

Why the trend across three filings matters more than one quarter

Reading the first three supplementals of 2026 side by side shows how fast the data center book grew and where it paused. Data center projects under development carried $1,740 million of expected investment at the end of the first quarter, $2,536 million at the end of the second and $2,588 million at the end of the third, all owned and managed figures from the filed tables. The power pipeline was 5.6 gigawatts in the first quarter (1.7 secured, 423 megawatts of it under development, and 3.9 in advanced stage), then 5.8 gigawatts in the second (1.6 secured, 680 megawatts under development, 4.2 advanced) and 5.8 again in the third. Data center starts this year total 1,966 thousand square feet and $2,091 million of expected investment, every one 100 percent leased at start: $1,289 million in the first quarter, $802 million in the second, and none in the third. The filing does not say why the third quarter had none, and PSV did not listen to the October 15 call, so this brief reports the filed numbers only.

A PSV bar chart titled Prologis data center builds, showing total expected investment in data center projects under development on an owned and managed basis: 1,740 million dollars at the end of the first quarter of 2026, 2,536 million at the end of the second and 2,588 million at the end of the third, with the source line Prologis supplementals, 8-Ks April 16, July 16 and October 15, 2026.
PSV CHART / PROLOGIS SUPPLEMENTAL INFORMATION, Q1 TO Q3 2026Data center projects under development rose from $1,740 million of expected investment at the end of the first quarter to $2,588 million at the end of the third, with no new data center starts in the third quarter. Chart: PSV, from Prologis supplemental information, Forms 8-K filed April 16, July 16 and October 15, 2026.

For an operator outside the data center business, the proportions are the story. PSV arithmetic from the same tables: data centers are about 33 percent of Prologis’ $7,884 million development portfolio by expected investment, and about half of the $4,089 million it has started this year at its own share. Prologis raised its 2026 guidance for development starts to $5.0 billion to $5.75 billion, from $4.5 billion to $5.5 billion, with a footnote that the deployment figures are inclusive of data centers, and raised acquisitions guidance to $2.1 billion to $2.3 billion. Net earnings guidance fell to $4.05 to $4.15 per share from $4.40 to $4.55, while Core FFO guidance narrowed to $6.25 to $6.29; the release does not explain the net earnings change. When a landlord of Prologis’ size treats utility capacity as a reportable asset class, every industrial site near a substation acquires a second possible use, and a second set of bidders.

The workflow PSV would run on these filings

The useful tool is a power claims register: one row per site or counterparty that says it has power, with the power split the way the claimant’s own definition splits it. Inputs are the quarterly supplementals and definitions of listed developers such as Prologis, a seller’s or broker’s offering materials, and utility correspondence the firm holds. Columns record megawatts claimed, the category the claimant uses (binding agreement, advanced discussions, application filed), the definition quoted verbatim, the quarter-over-quarter change, megawatts under development, expected investment, percent leased and expected completion year. The output is a short exception list: claims whose category is not backed by a binding agreement, and definitions that changed between filings.

The reviewer is the development or acquisitions lead who owns utility relationships for the market, and the approval gate is that no megawatt figure enters an underwriting model or an investment committee memo as secured unless the source’s own definition says the capacity is under a binding utility agreement. An assistant handles the volume work well: extracting the power and development tables from each 8-K exhibit, diffing them against the prior quarter, and flagging a changed footnote. It should not assign megawatts to a specific building, infer which sites sit in which markets, or treat advanced stage capacity as probable. PSV ran no model on these filings, tested no product, and promises no cost, schedule, yield or approval outcome.

What stays with a person, and what the filings leave open

The operator read

Finish with the judgment call.

The reported facts are above. Enter your email for PSV's operator conclusion and a year of access to every newsroom brief.

THIS ARTICLEALL PSV BRIEFSNO CARD REQUIRED
Send the operator read

Free. No card. Privacy policy. Unsubscribe anytime.

Dispatch the read

Keep the operator view in your deal room.

CRE AI Instituteby PSVLive

Build the workflow behind this analysis. Train with the operators doing it.

Real deal files, live builds, and production-ready CRE AI workflows inside the CRE AI Institute.

Clear answers

Common questions about Prologis Q3 2026 data center

How much data center power does Prologis have?

Prologis’ third quarter 2026 supplemental, filed October 15, 2026, reports a data center power pipeline of 5.8 gigawatts: 1.7 gigawatts of Secured Power, including 680 megawatts under development, and 4.1 gigawatts of Advanced Stage Power. Secured Power is utility-fed capacity under binding agreements with utilities. Advanced Stage Power is in advanced discussions with utilities, and Prologis states there is no guarantee it will become secured.

How big is Prologis’ data center development pipeline?

At September 30, 2026, Prologis reported data center projects under development of 2,182 thousand square feet and $2,588 million of total expected investment on an owned and managed basis, 100 percent leased, all expected to complete in 2027 or later. That compares with $1,740 million at the end of the first quarter and $2,536 million at the end of the second. By PSV arithmetic, data centers are about a third of its $7,884 million development portfolio.

Did Prologis start new data centers in the third quarter of 2026?

No. Its filed table of development starts shows no data center starts in the quarter. Year to date, data center starts total 1,966 thousand square feet and $2,091 million of expected investment, all 100 percent leased at start: $1,289 million in the first quarter and $802 million in the second. The filing does not explain the pause. Prologis raised its full year development start guidance to $5.0 billion to $5.75 billion, inclusive of data centers.

Primary source record

These records support the reported facts in this brief. PSV’s CRE workflow interpretation and test plan are original analysis.

Topics

CRE AI NEWSPrologis Q3 2026 data centerPrologis data center power pipeline 5.8 GWPrologis secured power advanced stage powerPrologis third quarter 2026 resultsindustrial REIT data center development

CRE CAPITAL NEWS

Prologis’ $18.8B SEGRO Deal: Power Is the Asset

Prologis agreed on August 4 to acquire SEGRO plc in a recommended share offer with a partial cash alternative, valuing SEGRO at approximately $18.8 billion. The press release sells European scale: 368 million square feet and a 126 percent larger European land bank. The Rule 2.7 announcement filed with the SEC names the thing scale does not describe, which is 2.5 GVA of power.

Read Prologis SEGRO acquisition data centre power rights

CRE AI NEWS

Brookings Paper Puts the AI Build-Out at $10.3 Trillion

A Brookings Papers on Economic Activity conference draft by Columbia real estate professor Stijn Van Nieuwerburgh, posted September 23 for presentation September 25, projects $10.3 trillion of U.S. AI infrastructure investment from 2025 to 2032, about 3.63 percent of GDP a year, and warns that the financing is moving into leases, joint ventures and special-purpose vehicles that are hard to see.

Read Financing the AI Buildout Brookings

CRE POLICY NEWS

Data Center Watch Q2 2026: $68B of Projects Disrupted

Data Center Watch, a research project of 10a Labs that tracks local opposition to data center development, says at least 45 U.S. projects worth nearly $68 billion were blocked or delayed by local opposition from April through June 2026. That is below its Q1 count of 75 projects and about $130 billion, but the first half of 2026 now exceeds its full-year 2025 total.

Read Data Center Watch Q2 2026

Cornerstone PSV guides on the workflows in this article.

Back to the CRE AI Newsroom
CRE AI Instituteby PSVLive

You read the operator view. Now learn to run the workflow.

The AI MBA for commercial real estate: the workflows these briefs describe, taught end to end on real deal files, with live builds and a community of CRE operators.